NLNG takes FID for Train 7

Nigeria LNG Limited (NLNG) on Friday  in Abuja took the Final Investment Decision (FID) for its Train 7 Project, which will increase its production by 35 per cent and its competitiveness in the global LNG market.

This decision allows the expansion to increase the capacity of NLNG’s six-train plant from the extant 22 Million Tonnes Per Annum (MTPA) to 30 MTPA, with the award of contracts for the engineering, procurement and construction activities to follow the closure of bank and Export Credit Agency (ECA) financing, and the finalization of some key supporting commercial agreements expected in early 2020. The actualisation of the Train 7 Project comes as NLNG celebrates 30 years of its incorporation and 20 years of safe and reliable operations since exporting its first LNG cargo in 1999.

NLNG is an incorporated Joint-Venture owned by four Shareholders, namely, the Federal Government of Nigeria, represented by Nigerian National Petroleum Corporation (49%), Shell Gas B.V.  (25.6%), Total Gaz Electricite Holdings France (15%), and Eni International N.A. N.V. S.àr.l (10.4%).

According to Tony Attah, MD/CEO of NLNG, “Train 7 is the crux of a growth agenda which will ensure the Company’s position as the 5th major supplier of global LNG is maintained, increasing value to its Shareholders and other stakeholders, as well as further reducing the gas that would otherwise have been flared, in fulfillment of its vision of ‘being a global company, helping to build a better Nigeria’”.

He further remarked that “over 12, 000 jobs will be created during the peak of construction, trade and commercial activities within the Niger Delta region equally receiving a boost as a result.  The Project will also support the development of local engineering and fabrication capacity in the country. Other opportunities for local content include procurement, logistics, equipment leasing, insurance, hotels, office supplies, aviation, haulage, and many more.”

The Company further remarked that the Project upon completion will support the Federal Government’s drive to diversify its revenue portfolio and generate more revenue from Nigeria’s proven gas reserves of about 200 Trillion Cubic Feet (Tcf).

The construction period after FID will last approximately five years with first LNG rundown expected in 2024

It would be recalled that Atta described  NLNG’s Train 7 project as the next big deal for Nigeria. Train 7 will increase NLNG’s production capacity by 35%, generating huge value for the company, shareholders and the country.

Speaking at the just concluded 9th Practical Nigerian Content Conference in Yenagoa said the project is coming into reality, adding “Train 7 is real; Train 7 is here. If you come to Bonny Island today, you will see that early site work has commenced and we are 97% prepared, just waiting to take that Final Investment Decision (FID)“.

He remarked that the relationship between NLNG and Nigerian Content Development and Monitoring Board (NCDMB) on the Train 7 project was that of a partnership for progress. He said: “We co-created the Nigerian Content Plan, working in harmony with the agency just to understand the interpretation of the law and then co-creating how we comply. Overall, it’s all about consolidation and co-creating the future. I am proud to say in March 2019, we signed off the Nigerian Content Plan for Train 7 project, delivering 100% Nigerian content in construction, production of cables, welding, valves, scaffolding, furniture, painting and medical. It is going to be 55 per cent of in-country engineering and procurement man-hours.”